November Business and Engineering Complex Update

November 13, 2018

Here are some of the major accomplishments achieved within the past 30 days:

  • The installation of the roof and multiple window units on the east side of the building.
  • Continued pouring of concrete decks on the west side of the building.
  • Installation of initial beams that connect the east and west sides of the building.
  • Installation of the limestone veneer along the east side of the building.

These are some of the anticipated major accomplishments for the next 30 days:

  • Continued installation of windows and exterior walls throughout the entire building.
  • Continued pouring of concrete decks on the west side of the building.
  • Installation of the limestone veneer along the north and south facades.
  • Terracotta sub-framing installation will begin on the east side of the building.
  • Continued installation of steel beams that will connect the east and west sides of the building.

On Monday, December 10 at approximately 3:00 p.m. we will hold a topping off ceremony as crews put the final beam in place atop the project. You are invited to join us for the brief ceremony if your schedule allows.