After the webinar, it was discovered that there was an omission on Slide 19 and 49 (“Late Entry” On-Ramps). Under construction Level 3, the statement:
“If there are open spots, completing registration requirements and submitting a proposal along with a BIM model developed to LOD 400 for the structural and pressure retaining elements is required to be considered – requests will be evaluated on a rolling basis”
...has been corrected to:
“If there are open spots, completing registration requirements and submitting a proposal along with a BIM model developed to LOD 400 for the structural and pressure retaining elements and to LOD 200 for the MEP and ECLSS is required to be considered – requests will be evaluated on a rolling basis”